Bombay High Court Buries Stalled Arbitration Proceedings Between Multiple Petitioners and Arrow Engineering.
23 April 2025
Arbitration Law >> Business & Commercial Law
Justice SOMASEKHAR SUNDARESAN, addressed a total of 22 such petitions, four of which were subsequently withdrawn. Of the remaining 18, three had been previously disposed of by a Learned Single Judge in an order dated October 12, 2020 ("October 2020 Order"), granting a mandate extension until November 1, 2021. Review petitions filed by Arrow against this order were later tagged with the remaining petitions.
However, subsequent to the October 2020 Order, the matter remained stagnant. The extended mandate expired, and no fresh petitions for further extension were filed by the involved parties. Recognizing the prolonged inactivity, the High Court, on its own motion, listed these long-pending petitions, initiating a process to determine their future.
The underlying arbitration stemmed from contracts where Arrow was tasked with constructing bungalows in the Navi Mumbai International Airport Influence Notified Area (“NAINA”), a project spearheaded by the City and Industrial Development Corporation of Maharashtra Ltd. (“CIDCO”). The Petitioners' primary claim in the arbitration was for a directive compelling Arrow to specifically perform these construction contracts.
However, no petition under Section 27 was ever filed in court. Instead, on October 29, 2017, the Petitioners applied to the Arbitral Tribunal for the termination of its mandate, citing their alleged inability to afford the arbitrator's fees. They also pointed to Arrow's purported financial difficulties in a parallel arbitration. Arrow contested this, arguing against termination based on unaffordability. A back-and-forth ensued regarding alleged prior consent from Arrow to terminate the proceedings, which Arrow later retracted following the arrest of its promoter. The Arbitral Tribunal ultimately rejected the Petitioners' application for termination in a detailed order dated January 17, 2018, deeming it unmaintainable and potentially setting an unhealthy precedent.
A petition under Section 29-A was eventually filed in August 2019, disclosing the fee situation and alleging Arrow was deliberately making the arbitration unaffordable. This petition sought both an extension and the substitution of the arbitrator but was later withdrawn with the liberty to file afresh, leading to the current set of petitions filed in October 2020.
The court also emphasized the October 2020 Order, which had already explicitly rejected the Petitioners' request for arbitrator substitution based on unaffordability, a decision the Petitioners did not appeal. The extended mandate granted in that order expired on November 1, 2021, without any significant activity in the arbitration. The Petitioners also failed to capitalize on the Supreme Court's suo motu extensions of statutory timelines during the Covid-19 pandemic to revive the proceedings.
Ultimately, Justice SOMASEKHAR SUNDARESAN concluded that sufficient cause for extending the mandate had not been demonstrated. The court deemed it appropriate to bring closure to the long-dormant arbitration proceedings by dismissing the petitions, allowing the litigants to move forward.
Section 29, Arbitration and Conciliation Act - 1996
Arbitration and Conciliation Act, 1996