Gurgaon Developer Ordered to Refund over 1.34 Crores for Delayed, Defective Unit.
18 October 2024
Consumer Complaints >> Civil & Consumer Law | Property Law >> Civil & Consumer Law
The complainants, Virender Singh Tanwar and Balbiri Devi, had booked a 3BHK unit in 2012, paying a total of Rs. 1,35,48,628 towards the agreed consideration of Rs. 1,57,97,215. As per the Floor Buyer’s Agreement, possession was to be handed over by June 2015, including a six-month grace period. However, the project faced significant delays, with construction stalling after March 2013 and no further payment demands being made until 2017.
In 2018, the developers offered possession, but with a catch: the super area of the unit had been unilaterally increased from 2,833 sq. ft. to 3,106 sq. ft., resulting in an additional demand of Rs. 78,15,445. Moreover, the terrace space had been converted into a room with a tin roof, transforming the 3BHK into a 4BHK without the buyers’ consent.
An independent inspection revealed severe deficiencies, including the absence of electrical wiring, flooring, and sanitary fittings, as well as the use of gypsum plaster, which led to dampness. The unit was deemed uninhabitable. Despite repeated complaints, the developers continued to demand additional payments without addressing the issues.
Citing precedents from the Supreme Court, the consumer court emphasized that buyers cannot be compelled to accept delayed possession or altered units. The court ordered the developers to refund the entire amount paid with 9% interest from the respective dates of deposit, along with Rs. 50,000 for litigation costs. Failure to comply within three months would result in a 12% interest rate on the outstanding amount.
Section 21, Consumer Protection Act - 1986