Supreme Court Clarifies Arbitrator's Powers on Interest Calculation in Arbitral Awards.
15 May 2025
Arbitration Law >> Business & Commercial Law
In a significant ruling on May 15, 2025, the Supreme Court of India, comprising Justice Abhay S. Oka and Justice Ujjal Bhuyan, addressed a crucial aspect of arbitration law: the power of an arbitral tribunal to award interest. The civil appeal, M/s. Interstate Construction v/s National Projects Construction Corporation Ltd.
Background of the Dispute:
The dispute originated from a contract between National Projects Construction Corporation Limited (NPCC) and M/s. Interstate Construction for the Ramagundam Super Thermal Power Project
The arbitration process was protracted, involving multiple arbitrator appointments due to delays and resignations
The Arbitral Award on Interest:
The arbitral tribunal awarded interest under three heads
- Pre-reference/past period interest: At 18% per annum on Rs. 34,43,490.61 from July 1987 until January 19, 1998
. - Pendente lite interest: At 12% per annum from January 20, 1998, until December 31, 2008, and again from January 1, 2017, till the date of the award. This interest was calculated on the total amount (principal + pre-reference interest)
. The tribunal explicitly excluded interest for the period from January 1, 2009, to December 31, 2016, citing "complete laches" on the part of the appellant in pursuing its claims . - Future interest: At 18% per annum from the date of the award till payment, on the total amount (principal + pre-reference interest + pendente lite interest)
.
Delhi High Court's Decision:
NPCC challenged the arbitral award before a Single Judge of the Delhi High Court under Section 34 of the Arbitration and Conciliation Act, 1996
Aggrieved by this, NPCC appealed to the Division Bench of the High Court under Section 37 of the 1996 Act
The Division Bench allowed NPCC's appeal, setting aside the directions in paragraph 58(b)
- Periods for Interest: Section 31(7) of the 1996 Act recognizes only two periods for interest: from the date the cause of action arose till the award, and from the award date till payment. Thus, the arbitral tribunal erred by carving out three periods (pre-reference, pendente lite, and future)
. - Compound Interest: The tribunal committed an illegality by "forging the principal amount with interest" (i.e., levying interest on previously accrued interest), which amounted to impermissible compound interest
.
Supreme Court's Analysis:
The Supreme Court found the High Court's reasoning "fallacious"
Interpretation of Section 31(7) of the 1996 Act (Periods for Interest)
The Court referred to Section 31(7) of the 1996 Act, particularly clause (a), which allows an arbitral tribunal to award interest "for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made"
The Court cited its recent decisions in Pam Developments Private Limited v. State of West Bengal
Compound Interest (Interest on Interest)
On the issue of compound interest, the Supreme Court noted that this matter is "no longer res integra"
The Court reiterated its conclusion from S.A. Builders Ltd. that the "sum" awarded by the arbitral tribunal, which may include interest from the date of the cause of action to the date of the award, would carry further interest from the date of the award to the date of payment
Conclusion:
Based on this comprehensive analysis, the Supreme Court concluded that the impugned judgment of the Division Bench of the High Court dated August 1, 2023, could not be sustained
Arbitration and Conciliation Act, 1996