Supreme Court Directs Expeditious Resolution in Bank Guarantee Dispute, Upholds Interim Protection.
07 May 2025
Arbitration Law >> Business & Commercial Law | Civil Appeals >> Civil & Consumer Law
The dispute originated from a work order issued by the appellants to Respondent No. 1, M/s. Bansal Infra Projects Private Limited, on January 24, 2022, for the construction of 400 flats at Jindal Nagar, South Block (Sharmik Vihar), valued at over Rs. 43.99 crores. An advance of Rs. 3,73,95,490/- was provided to Respondent No. 1, secured by an unconditional bank guarantee dated March 8, 2022.
The project, initially slated for completion by September 30, 2022, saw multiple extensions, with the final deadline extending to September 30, 2023. The appellants terminated the work order on July 7, 2023, citing Respondent No. 1's alleged poor performance, including quality deficiencies, missed deadlines, and non-compliance with contractual obligations. An amended work order was subsequently issued on July 13, 2023, which included a condition for the forfeiture of retention money if the handover extended beyond September 30, 2023.
Following continued issues, on February 21, 2024, the appellants highlighted disregard for construction norms by Respondent No. 1 and, on March 25, 2024, demanded a refund of a debit balance of Rs. 4,12,54,904/- due to unadjusted advances and other deductions by April 30, 2024, failing which the bank guarantee would be encashed.
Aggrieved by this, Respondent No. 1 filed a writ petition (W.P. (C) No. 11844 of 2024) under Article 227 of the Constitution before the High Court of Orissa. The High Court initially granted an interim order of status quo regarding the encashment of the bank guarantee. Subsequently, on August 20, 2024, the High Court disposed of the writ petition, directing the Commercial Court to expedite the Section 9 petition and maintaining the interim order restraining the bank guarantee's encashment until its disposal, contingent on Respondent No. 1 extending the bank guarantee.
Respondent No. 1, conversely, argued that the Commercial Court's order was an interim measure, not a final order under Section 9, and thus not appealable under Section 37. They also highlighted that the alleged non-compliance was due to delays caused by the appellants, leading to the High Court's finding of "special equities" in their favor.
Crucially, Respondent No. 1 has extended the bank guarantee until June 30, 2025, and has undertaken to further extend its validity until the disposal of the Section 9 arbitration petition. Given that no prejudice is currently being caused to the appellants, the Supreme Court opted not to decide the complex legal questions raised by the parties, leaving them open for future consideration.
Section 9, Arbitration and Conciliation Act - 1996
Section 37, Arbitration and Conciliation Act - 1996
Arbitration and Conciliation Act, 1996